June '99
This page describes work accomplished on the new TMRC layout during the month of June 1999, as taken from the descriptions posted to the club mailing list.
June 12

Alvar began to work on the new crossover switch out of the west end of P-yard. This new switch is a curved crossover which was previously deemed impossible due to the raddii, but which is being done with a little of magic (and by letting the radius be around 35" instead of 36" :-). Unfortunately this switch makes mainline virtually unoperable, therefore teh mainline is out for 2 or 3 weeks... But to help Alvar in his efforts Jeff quickly wired the new crossover in System 2, it is now switch #38.

Meanwhile Bill continued work on the vegetable oil facility. Andy worked more on the Gifford City station. He worked on the second street, which is the one that will have the stairs down to the platforms. Talking about stairs, Andy now has the handrails for the stairs down to the platforms. John Shriver was also here, and continued to expand the Bitco rail, almost reaching the carbarn!


June 16

John P. demonstrated a prototype model of the lift bridge he intends to build across the river at the entrance to the clubroom. The model is fully (manually) operational, and is a great proof of concept that shows that the bridge can truly be a reality! Later on JP worked on a sample facia for the layout (that holds the Lexan front to prevent little fingers from derailing the trains. He also added switch #38 to the layout description in the new S-board.

Both James and Alvar worked on the TMRC computers... the damage was all repaired by the end of the day!


June 19

Alvar continued the work on switch #38, the new crossover that allows more than two trains out of the west side of Gifford City at a time. One switch is complete, but the switch with a movable frog is not yet ready, that's for next week! Jeff wired the last part needed for the System 2 side of the switch.

Since JP's sample fascia of the layout was very well received by all the members, he built another piece, and is starting to device a 'mass production' system to make it easy to build these. Bill Onorato continued his work.


June 23

Alvar finished the trackwork on switch #38, including a moving point! Say hello to the infinite loop again :-)


June 26

John Shriver worked down the curve of Gifford City laying down trolley track. He has now reached the carbarn, next step: switch ladder! Working right next to John (and under him, and around him, and all over the place), Alvar finished switched 38, including all the electronics. The layout is fully operational again! Of course, Alvar did not do it alone. Jeff was great at finding all those silly mistakes that are made in any project. Justin searched for more TMRC equipment, and put the MIRTA equipment into operation. Bill O. continued his work.


June 30

James and Alvar attended the summer mailing 'stuffing party', and (mainly James) stuffed about 1000 fliers that will go to all the incomming freshmen. Afterward they met with Jonh P. in the clubroom. John P. checked a couple of small gage problems in crossover 38 (the new one), and subsequent switches in the same ladder, which were not quite to standards. We had several visitors that night, so we entretained them with trains that could run all around the layout again!



Previous MonthNext Month
Calendar
2018
JanFebMarApr
MayJunJulAug
SepOctNovDec
2017
JanFebMarApr
MayJunJulAug
SepOctNovDec
2016
JanFebMarApr
MayJunJulAug
SepOctNovDec
2015
JanFebMarApr
MayJunJulAug
SepOctNovDec
2014
JanFebMarApr
MayJunJulAug
SepOctNovDec
2013
JanFebMarApr
MayJunJulAug
SepOctNovDec
2012
JanFebMarApr
MayJunJulAug
SepOctNovDec
2011
JanFebMarApr
MayJunJulAug
SepOctNovDec
2010
JanFebMarApr
MayJunJulAug
SepOctNovDec
2009
JanFebMarApr
MayJunJulAug
SepOctNovDec
2008
JanFebMarApr
MayJunJulAug
SepOctNovDec
2007
JanFebMarApr
MayJunJulAug
SepOctNovDec
2006
JanFebMarApr
MayJunJulAug
SepOctNovDec
2005
JanFebMarApr
MayJunJulAug
SepOctNovDec
2004
JanFebMarApr
MayJunJulAug
SepOctNovDec
2003
JanFebMarApr
MayJunJulAug
SepOctNovDec
2002
JanFebMarApr
MayJunJulAug
SepOctNovDec
2001
JanFebMarApr
MayJunJulAug
SepOctNovDec
2000
JanFebMarApr
MayJunJulAug
SepOctNovDec
1999
JanFebMarApr
6 12 13 16 20 23 27 3 10 13 17 20 24 27 10 14 17 20 24 27 31 3 7 10 17 21 24 28
MayJunJulAug
1 8 15 12 16 19 23 26 30 3 7 14 17 21 24 27 31 3 10 14 17 21 24 28 31
SepOctNovDec
4 11 18 21 25 2 5 12 16 19 23 2 6 9 20 7 11 22 29
1998
JanFebMarApr
MayJunJulAug
SepOctNovDec
1997
JanFebMarApr
MayJunJulAug
SepOctNovDec

Tech Model Railroad Club of MIT
MIT Room N52-118
265 Massachusetts Avenue
Cambridge, MA 02139

+1 617 253-3269
Email: tmrc-web@mit.edu